FACILITY DESIGN
CICMHE puts on an annual design competition in which teams are supplied with a case for a company’s facility problem. Teams propose a new facility design solution meeting the requirements of the company. My primary role was designing the facility in AutoCAD and involved analyzing current facility product volume and space requirements as a baseline for the new facility design.
Problem Statement
At 95% storage occupancy, Fresh Foods Now (FFN), is in need of a new warehouse that can improve storage capacity and account for growth in the future. FFN is dealing with efficiency issues in the current warehouse, and also could be losing possible customers with not enough room growth. With additional space, more items can be stored by FFN and allow for greater sales of those items that have been direct to store. The new facility layout needs to accommodate for new inventory items, as well as reduce the occupancy of the original warehouse to allow for greater efficiency, and finally, allow for the introduction of more items with an anticipated growth of 5.5% annually.
Conceptual Design
When designing the layout, I had to account for initial product volume as well space requirements to facilitate future growth. I utilized Richard Muther's Systematic Layout Planning (SLP) and the Engineering Design Process to most effectively design the facility and meet the client's requirements. Additionally, my objective was to ensure all department relationships marked as A and E were met throughout the process.

Relationship Chart
Depicts the importance of department locations based on their required proximity.


Space Relationship Diagram
Constructed to visually show the flow between departments.
Block Layout
Final block layout drawing for the new facility based off of the relationship diagram and chart.

System-level & Detailed Design
Breakdown of departments, offices, utilities and racks

In/Out docking area and cross-docking designated in the center.

Includes cafeteria and bathrooms. I determined the size requirements to account for maximum personnel usage.

Reserve goods stored to replenish forward area.

In/Out docking area and cross-docking designated in the center.
Final Warehouse Design
Overhead Facility View


3D without racking
I designed contained areas for the alcohol and perishable departments that required refrigeration.
3D with racking